Planning projects in Shellharbour City
32 State significant and State-assessed projects in Shellharbour City are listed on the NSW Planning Portal. None are on public exhibition right now. Council-assessed local DAs aren't included.
Open for submissions
Nothing in Shellharbour City is on exhibition right now. See everything open across NSW.
Coming up for exhibition
These projects are being prepared for public exhibition. Organisers who start early are ready the day submissions open.
Prepare EIS
Mixed Use Development at 29 Shellharbour Rd & 25 Grove Cct, Lake Illawarra
Construction of a 14 storey mixed use development with approximately 186 units and 13% affordable housing.
Shellharbour CitySSD-134489990
Recently assessed or decided
Withdrawn
Shellharbour Hospital Expansion
Construction of a new Acute Services Building (ASB) up to five storeys in height and including a rooftop helipad. Refurbishment of parts of the existing hospital building, construction of a multi-storey carpark (up to 5 storeys) and associated works
Shellharbour CitySSD-9808
Withdrawn
DHRQ Croome Nth and Sth Expansion Project
Expansion of the existing extraction pit by 37.5ha and increase in the depth of extraction
Shellharbour CitySSD-9094519
Withdrawn
Sydney Trains' Dunmore Hard Rock Quarry
The proposed quarry would utilise conventional drill and blast, load and haul and processing methods to produce up to 1Mtpa of quarry products with a mobile plant positioned adjacent to the resource area.
Shellharbour CitySSD-8603
Withdrawn
Bass Point Quarry MOD 5 - Solar Panel System
Hanson propose to develop a solar panel system at the Bass Point Quarry site. The proposed system would: • Have a general capacity of 5MW • 2MW will power Bass Point Quarry with the 3MW remainder offset recirculated into the grid.
Shellharbour CityMP08_0143-Mod-5
Determination
Bass Point Quarry MOD4 - Alternative transport route
Use of the Bass Point Tourist Road site access to supply quarry products - via NSW registered heavy vehicles - specifically to the Bass Point Tourist Road Upgrade Project.
Shellharbour CityMP08_0143-Mod-4
Determination
Albion Park Quarry - Stage 7
The project involves the ongoing operation of the approved Stages 1 to 6 of the existing quarry and a proposed Stage 7 extension area.
Shellharbour CitySSD-10369
Determination
Bass Point Quarry (MOD 3) - Amenity barriers
Amendment to Location of Amenity Barriers
Shellharbour CityMP08_0143-Mod-3
Determination
Modification 13 Dunmore Quarry Pit Extension
Extension of the quarry pit to the north, increase in extraction depth and extend quarry life to 2043.
Shellharbour CityDA470-11-2003-Mod-13
Determination
Mod 6-Aggregate Recycling
Importation of up to 200,000 tonnes per annum of waste concrete and other materials to the Bass Point Quarry site for processing as recycled aggregate.
Shellharbour CityMP08_0143-Mod-6
Determination
New Shellharbour Hospital
Construction and operation of a new hospital development including landscaping, internal roads and access, at-grade and multi-deck car parking, utility/service connections and supporting infrastructure.
Shellharbour CitySSD-57064458
Determination
MOD 2 - Dunmore Lakes Quarry
Dunmore Lakes Quarry (Mod 2)
Shellharbour CityDA195-8-2004-Mod-2
Determination
Bass Point Quarry MOD 2 - Truck Movements
Minor increase in truck movements
Shellharbour CityMP08_0143-Mod-2
Determination
Bass Point Quarry MOD 1 - Bass Point Quarry
Bass Point Quarry (Mod 1)
Shellharbour CityMP08_0143-Mod-1
Determination
Albion Park Quarry MOD2 - Increased Production Rate
/
Shellharbour CityDA10639/2005-Mod-2
Determination
Albion Park Rail Bypass - Mod 1 - Property Surveys
This modification is to change the requirements about when both building and structure condition reports (E51) and road dilapidation surveys (E75) be undertaken.
Shellharbour City+1 moreSSI-6878-MOD-1