Search results
Showing NSW Planning Portal projects in Muswellbrook Shire.
97 projects · page 1 of 9
Closes 26 Nov · 20 days left
New England REZ Transmission Project
Development of new dual 500kV transmission lines between Muswellbrook and the New England REZ and new 500kV and 330kV lines to connect five new energy hubs within the New England REZ. This project is declared CSSI.
+6 moreSSI-74175972
Assessment
Dalswinton Sand and Gravel Quarry
Development of sand and gravel quarry extracting up to 500,000 tpa for 25 years
SSD-9094
Assessment
Dartbrook Coal MOD9 - Temporary Road Haulage
Short-term road haulage of product coal (as a temporary alternative to the approved method of rail transportation) and amending maintenance obligations for historical heritage items due to a change in land ownership
DA231-07-2000-Mod-9
Assessment
MOD1 - Liddell Ash Dam Toe Drain Works
Construction and ongoing use of drainage works at the Liddell Ash Dam toe drain as part of the project and administrative amendments to the consent
SSD-24937520-Mod-1
Assessment
Muswellbrook Battery Energy Storage System Mod 1
Minor changes to the layout plan to reflect access upgrades to accommodate changes to delivery vehicle sizes, updates to mapping, and increasing noise barrier heights.
SSD-29704663-Mod-1
Assessment
Mod 8 - Link Road Realignment Adjustment
Modification 8 involves adjustments to the realignment of Bengalla Link Road
SSD-5170-Mod-8
Response to Submissions
Upper Hunter South Solar Farm
Construction, operation and decommissioning of a 90MW solar farm, 30MW / 60 MWh battery energy storage system and associated infrastructure
SSD-65996959
Response to Submissions
Upper Hunter Battery Energy Storage System
Battery Energy Storage System (BESS) with a capacity of 400MW/ 920MWh and associated infrastructure
+1 moreSSD-61707209
Response to Submissions
McCullys Gap Battery Energy Storage System
Construction, operation, and decommissioning of a Battery Energy Storage System with a capacity of approximately 400 MW/1600 MWh, and ancillary infrastructure.
SSD-81555720
Response to Submissions
Bowmans Creek Wind Farm Stage 2
Development of a wind farm with up to 21 wind turbines and associated infrastructure.
+1 moreSSD-73123714
Response to Submissions
Denman Battery Energy Storage System
Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 2.4GW/4.8GWh and ancillary infrastructure.
SSD-76189216
Prepare Mod Report
MOD 1 - Battery Energy Storage System
Addition of a Battery Energy Storage System (BESS) and the modifications to sections of the main access route to accommodate OSOM vehicles
+2 moreSSD-10315-Mod-1